Dudley StationProject Summary: Demolition, Orange line Track and Structure, Boston, Massachusets

Owner: Metropolitan Bay Transportation Authority

Requested Service
: Performance extension analysis, disruption claim formulation, major rapid transit demolition project.

Engagement
: Did computerized dismantlement simulation as originally planned, compared with as-built performance.  Planned performance was non-existent; nullified by owner caused schedule disruption.  Performed engineering estimate of damages.  CPM schedule analysis.

Issues: Active interference, superior knowledge, misrepresentation, recovery under quantum meruit

Claim Value
: $4MM range