|
|||||||
|
|
Home
>>
Eichleay White Paper >>
Eichleay
Eichleay And The Recovery of Unabsorbed Home Office Overhead: The Redheaded Step-Child Among The Various Elements of Compensable Damages In Putting A Small Contractor’s Home Office Overhead In Perspective Often like the parent of the aforementioned proverbial child, a contractor, particularly early in its life, and in highly competitive tight markets as well, may tend to ignore its G&A cost.1 For example, a less experienced contractor in need of new work may “bid the competition” to an extreme. He tends to figure his direct costs down to a fine line, put on some figure, say 10%, for indirect field cost, supervision, field office, etc., then, in an attempt to best the competition and without much thought to the fact his G&A cost record actually is based on his previous fiscal year-end financial statements, adds on another say 7% for “margin”. Margin, by necessity then must cover profit and G&A. Under these circumstances, any major government disruption or suspension prolonging the contract’s performance can burn down the margin between cost and contract income such that there ultimately remains nothing for profit ….or worse. Home Office Overhead – A “Dead Horse” Which Must Be Carried The Government Gauntlet A Contractor Faces In An Unabsorbed Overhead Recovery Attempt Before jumping into the government claims ring to challenge this cast of government actors, one had best gird his loins for combat. Knowing exactly what you are claiming, and the support for it, is indispensable. Having a rock-hard, air-tight case factually and legally will help.5 Otherwise you will waste your time and money. Eichleay Explained “Over 40 years ago, in Eichleay Corporation, ASBCA No. 5183, 60-2 BCA 2688, qffirmed on reconsideration, 61-1 BCA 2894, the Armed Services Board of Contract Appeals ("ASBCA") recognized that there is no exact method to determine the amount of home office overhead expenses to be allocated to any particular contract. In Eichleay, the board utilized the following formula for allocating extended home office overhead costs to a contract that has been delayed: (1) [Contract Billings / Total Billings for Full Contract Period] x Total Overhead for Contract Period = Overhead Allocable to Contract (2) [Overhead Allocable to Contract / Total Days of Performance (including Delay Period)] = Daily Contract Overhead This formula for calculating extended home office overhead damages is commonly called the "Eichleay Formula." The Federal Circuit has approved the use of the Eichleay Formula to calculate extended home office overhead ... "provided that compensable delay occurred, and that the contractor could not have taken on any other jobs during the contract period." C.B.C. Enterprises, Inc. v. United States, 978 F.2d 669, 673-4 (Fed. Cir. 1992).” Eichleay – A “Resilient Means” “The mathematical operation of the EichIeay formula is best understood by
“99. Westlind calculated its total billings by determining a per diem rate of total 100. Westlind calculated its total overhead by determining a per diem rate of total A chart of this creative approach might be helpful to visualize how this method nullifies the dispute potential which would be natural in the identification of exactly where the start and stop points for the correct total overhead figure actually occur in the contractor’s financial statements: Note that the Board’s only apparent criteria for the contractor in this regard was that the actual performance start and stop within “the [fiscal] years during which it performed the contract”. The DCAA Watchdog Watching Eichleay “The actual contract performance period represents the actual days of performance (including the extension period). It is the period from the start date of the contract until the date of contract completion. Note that the contract billings, total billings, the total fixed overhead and the performance days should be for the same time interval, i.e., the delayed contract’s actual total performance period.” At least part of the reason why the DCAA auditors’ findings sometimes seem unreasonable is because their own Manual has flaws. For example, a serious auditor, an astute student of his DCAA Manual,12 might demand that the contractor produce proof that he could take on no other work while standing by during the government-ordered suspension of contract work:13 “Entitlement to Unabsorbed Overhead Damages. The U.S. Court of Appeals of the Federal Circuit (CAFC) (West v. All State Boiler, 146 F.3d 1368 (Fed. Cir. 1998) “All State”) ruled that the elements of the claim (legal tests) that a contractor must show to recover unabsorbed overhead include: (1)The delay/suspension was Government caused [when a Government caused disruption results in a delay of contract performance, Eichleay damages may be appropriate]. (2) The Government required the contractor to standby during the delay/suspension period. (3) It was impractical for the contractor to take on other work. (4) The delay/suspension caused the contractor to be unable to complete the contract within the original contract performance period, as extended by any modifications.” In fact, the actual rule as to what a contractor must prove is no such thing.14 (Going forward from this point, I refer from time to time to my contractor-example. See fn14.) The government had constructively admitted it was solely at fault. The suspension was sudden and the contractor was always in doubt about its duration. As a result, it was not possible to take on “replacement” work with the assets planned for use on the instant contract. Thus he was always in stand-by mode for the suspension’s duration. The contractor had a prima facie case for recovery of his unabsorbed G&A. Once this is established, no proof by the contractor of items (3) and (4) above is required. They are assumed as true and shifted to the government for rebuttal proof:15 “Therefore, when a contractor can show that the government required a contractor to remain on "standby" and [show that] the government-imposed delay was "uncertain," the contractor has established a prima facie case of entitlement to Eichleay formula damages. The burden then shifts to the government to present rebuttal evidence or argument showing that the contractor did not suffer or should not have suffered any loss because it was able to either reduce its overhead or take on other work during the delay.” Key Issues For Our Suspended Small Contractor The Exception To The Federal Circuit’s Eichleay Exclusivity Rule The Federal Circuit did note, however, that the contractor nevertheless might be able to recover unabsorbed overhead through "some other method of allocation,"17 making Eichleay off limits for any contractor so unlucky as to be the winning bidder on any contract on which the government has unknown (or concealed) design or site access issues which must be fixed before a formal Notice to Proceed (“NTP”) can be issued, and/or before any actual work can be accomplished.
Our contractor’s contract is on a Department of Defense agency contract. His claim will by definition be a Contract Disputes Act (“CDA”) claim, the statute of limitations for the submittal of which is six (6) years from the date of its accrual, provided in the interim he declines to accept any government offer of “final contract payment” and release of claims.20 A simple explanation of why the government is being just a bit disingenuous with its demand for a rush-to-submittal may be that it wishes to unfairly minimize its unabsorbed overhead damages exposure.21 Contractor blunders made in producing REAs in an unreasonably constricted time frame will facilitate this, as such blunders are broader targets for the CO’s claim defense-savvy technical and legal helpers to aim at. Nothing discredits a claim like money damages generated by contractor overreaching – done innocently or not. Taken to the extreme, the government has a penchant to threaten, and sometimes actually file, counterclaims alleging contractor fraud, many of which are withdrawn upon the contractor’s agreement of claim forfeiture. Does Government Bias Exist In Contract Administration? FAR 52.242-14 states:24 (a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government. (b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract. Question #1 - If it has been determined that the delay is both excusable (Defaults clause) and compensable (Suspension of Work clause), what is the best way to isolate the costs that should be considered for providing relief of actual costs for FOOH, Design and/or HOOH as a result of the delay? Typically contractors try to load up a cost pool to come up with a daily rate and then multiply times the number of days of delay. However, if there is no idle equipment and only very limited labor costs as a result of suspension, is there anything due the contractor? Question #2 - What would be the reasons to NOT issue a suspension of work, if you know there is going to be a delay in giving NTP or allowing some part of critical path works to commence? Isn't the contractor already on notice about suspension at the convenience of the Gov't, by virtue of the clause being in the contract? [Highlights and footnote added.]
This bureaucrat is clearly biased; they “try to load up a cost pool”, says he, seeking to maximize their home office overhead (“HOOH”) recovery. This is next to impossible. Because the allocable pool will have to be stripped out of the contractor’s existing financial statements prepared by his accountant at either the “review” or “audit” level, challenged and further stripped of non-FAR-compliant entries by the contractor’s consultant; and finally thoroughly challenged by the DCAA auditors, padding the pool would be folly and might even bring down a fraudulent claim case from the government. He has the contractor-biased bright idea that when essentially no work has been performed, and the government can show essentially no direct costs have been expended by the contractor; and (probably also) when no billings have thus been generated as a result to install into the Eichleay formula, he wants to know if the government can’t simply go into denial by failing to issue the Suspension of Work Order. He believes this would nullify the contractor’s key element to its prima facie entitlement case, i.e., that government-caused suspension even exists. He is looking for some peer-blogger to support this. More Government Contract Administrators Than Not Aim At Professionalism
Government Contracting In The Real World – The Stunning Negative Impact Of Major Contract Suspension On Small Contractors Meanwhile, a pre-government contract work program which had been steadily throwing off about six to eight million cash income each year, had wilted to a mere dwarf of its previous self, the $8MM government contract part paralyzed for eight (8) months. This much stifled income for this long translates directly to drastically reduced corporate retained earnings, which will not be transparently apparent until the next fiscal year-end financial report. This is when, at the latest, working capital and surety bond lines will be reviewed by his banking and bonding support. Retained earnings on his new financial statement will have melted from the previous report to smaller than Al Gore’s prediction of the polar ice caps in the worst case global warming scenario. Unless these contractor supporters are beyond exceptional, the bond company will demand a major personal cash infusion into the corporation by the principals - just to maintain the current bond level. Next, the bank will want more property pledged as working capital collateral. As for what the government cares about this unfair situation, he could interview all the government bureaucrat authorities25 all the way up to the department secretary, present them with this unjust situation, and in return get only blank stares. There is no hope that any recovery of contract damages he may ultimately prove and eventually receive will completely make whole the final corporate damages which will result. He has no choice but to march on, completing the government contract while essentially financing it in the process, meanwhile vigorously pursuing the REA – and/or ultimately, the CDA-certified unabsorbed overhead claim – and financing that as well. Never Forget – In Government Contracting It Is The Government Who Is In Control Of The Small Contractor’s Business Continuity, NOT The Contractor To illustrate, both Nicon17 and our contractor were small contractors. Both were awarded Government contracts. Both contracts were suspended by the government before any work could start. Both suspensions were for the better part of a year, ours for eight months, Nicon’s for 288 days. Both were placed in a standby position by the government. Both being small contractors, the instant government contract of each was a major financial element in its overall surety bonded work program. Both had (have) a prima facie case for entitlement to unabsorbed overhead.26 Failure of reasonably prompt, fair, recovery of resulting damages by either may well be critical to its contracting business continuity.27 Further To The Nicon Saga Meanwhile over this course of time, two different construction claims consulting firms had been applying their considerable expertise to the case on Nicon’s behalf. Both claim in their current advertising they made positive contribution to the case, one apparently consulting with Nicon’s attorney to negotiate $184,757 in direct field costs and “related overhead” at the lower court in 2001, while the other directed its service to cooperation with Nicon’s attorney in pursuit of the $387,513 in unabsorbed home office overhead before the second, appeals, court. As of June 2003, after over five (5) years of negotiations supported by the not inexpensive services of three (or four) claims and legal advisors, Nicon was now faced with seeking fairness and justice before the same lower court which had on summary judgment30 dismissed the case two years earlier. Nicon was now facing another year at least before briefing could be completed and the court would produce a ruling. Since I can find no record of Nicon’s appearance before the lower court again, I reasonably conclude that Nicon cut its losses and made some final deal with the government for enough to perhaps cover its legal and consulting costs, and together they petitioned the court for dismissal, ending the issue. Some Layman’s Insight Into The Contradictions Within The Federal Claims Tribunals Since early in the previous decade, the various boards of contract appeals have been re-charted by Congress as being peer tribunals with the current U.S. Court of Federal Claims (“Claims Court”), the lower court to which Nicon initially brought its claim. Contractors, even before the time Congress made the change, had a choice; they could, and can now, bring appeals from a CO’s decision to either the Claims Court or to the appropriate board of contract appeals. Since the time Congress made this change, the appeals of contractors whose claims are denied at either the boards or at the Claims Court must make their final appeal to the Federal Circuit Court of Appeals. Before that time, contractors with rejected claims at the boards made their appeals to the Claims Court (under its various earlier names). It has been said by various legal writers that this situation has been non-conducive to almost any cross proliferation of case law after the Congressional change of court-board peer standing. The boards generally ignore the precedents set by the Claims Court and vice versa. This lengthy explanation sets the stage for analysis of the following hypothetical scenario. Suppose Nicon had chosen to appeal its CO’s decision to the Armed Services Board of Contract Appeals (ASBCA”), not the Claims Court. Had it done so, there is a strong likelihood the ASBCA would have found for Nicon, not summarily dismissed the case as did the Claims Court.31 In The Appeal of – Genisco Technology Corporation, ASBCA No 49664, April 7, 1999,32 the ASBCA emphatically found that estimates of elements of an Eichleay formula, when actual figures were not available, were permissible. The contractor had met a situation like Nicon’s; there had evidently been an award protest, and the contractor had calculated unabsorbed overhead by other means, avoiding Eichleay on the excuse, exactly like in Nicon, and our contractor’s situation, there were no billings as the contract had been suspended by the government before any could be generated: Appellant seeks reconsideration of our decision denying its appeal. In Genisco Technology Corporation, ASBCA No. 49664, 99-1 BCA 30,145 (Genisco), we denied appellant’s claim for unabsorbed overhead because it had not been computed using the + formula, and we concluded that use of the Eichleay formula was mandatory, citing West v. All State Boiler, Inc., 146 F.3d 1368 (Fed. Cir. 1998) and Libby Corporation, ASBCA No. 40765, 96-1 BCA 28,255. Genisco also rejected the modified Eichleay computation appellant presented at the hearing because we found the computation to be based on financial data that was seriously incomplete. Appellant alternatively requests that we reopen the record to receive additional financial data and a revised Eichleay computation. Respondent opposes both reconsideration and the reopening of the record. The parties have submitted a considerable quantity of additional material with the motions and opposition. THE MOTION FOR RECONSIDERATION Appellant next argues that our decision effectively eliminates FAR 52.233-3 from the contract. As stated above, decisions of this Board and our appellate court have adjudicated claims under FAR 52.233-3 using the Eichleay formula. Other decisions of this Board and our appellate court have held that unabsorbed overhead may only be calculated by use of the Eichleay formula. Our view is that a common sense reconciliation of those decisions to FAR 52.233-3 would result either in submission of unabsorbed overhead claims thereunder by use of estimates, or with the agreement of the contracting officer that he or she will consider such claims after 30 days but before final payment, as the clause provides. We are unpersuaded by appellant’s argument that, under Genisco, a contracting officer could never award unabsorbed overhead pursuant to FAR 52.233-3 because a contractor would never have enough information to file an Eichleay claim. As pointed out above, even the DCAA Audit Manual recognizes that estimates will be used in Eichleay calculations. Notably, twice, the ASBCA pointed to “decisions of … our appellate court [the Federal Circuit]” as predicate for mandatory use of Eichleay for figuring unabsorbed overhead. ASBCA pointedly stated that it has held in a previous case that “claims based on estimates” are acceptable. Finally, “…even the DCAA33 ….recognizes…” Eichleay calculated with estimates, said the ASBCA.34 Government Contract Administrators Disingenuous Behavior And Its Impact On Small Contractors “Toto, I’ve A Feeling We’re Not In Kansas Anymore” 38 How did government contract justice get to be this way? Is three courts, six years and final resolution for pennies on the dollar in “negotiations”39 with the government agency which created the stalling and delaying tactics in the first place, fair?40 Who will serve notice on government and its mega-prime contractors they must not use sly bullying tactics like fictitiously short submittal periods to facilitate government advantage in negotiations? What’s with this thing with the lower peer tribunals where each ignores the decisions of the other? What’s with the mighty Federal Circuit which perpetuates this ridiculous situation? Why do we even need the boards if the Claims Court is permitted to ignore their decisions as if they don’t even exist? Or vice versa? Which lower tribunal should our contractor choose if fairness can’t be found at the CO level? He will need to decide that immediately. But how could he make that decision? If he calculates the claim by estimating the financial and time elements required in the Eichleay and brought that to the ASBCA in appeal from a negative CO decision, would the board stand by its Genisco decision or would it immediately buckle in deference to the Federal Circuit’s current position that Eichleay cannot be used where no contract billings have been generated? If the board upheld the contractor’s use of estimates, the government would surely appeal to the Federal Circuit. Would the Circuit then do as in Nicon and simply run it back to the board to determine another way to make the calculation? Can anyone guess the time which would elapse in this tortured process? These and similar questions stand starkly begging for answers. I hope and plan to address some of them or ones similar in the very near future. Your comments are graciously invited. Glen L. Eaton _____________________________________ 1. He does so at his own great peril. “Overhead for many contractors is a completely nebulous item that is felt rather than seen and measured. It should not be so for overhead alone may well run up to 10 percent of a contractor’s annual business volume.” Contractor’s Management Handbook, James J. O’Brien and Robert G. Zilly, 1-17. 8 III. The Eichleay Formula: A Resilient Means For Recovering Unabsorbed Overhead, 322 Public 9 This is an exact calculation based on the root figures in …A Resilient Means...., which showed 15 Mech-Con Corp. v. West, 61 F.3d 883, 14 FPD _ 65, 19 C.C. _ 395 (Fed. Cir. 1995). 19 Mega-prime government contractors, and other primes as well, are not noted for sharing with their subs 24 FAR: Federal Acquisition Regulation. 25 If they could be found. 29 The appearance of two different consulting firms at two different courts addressing the same or related 31 True, the same ultimate result might have occurred if the government were to have appealed a ASBCA 33 With obvious reverence for the weight that venerable government watchdog throws. 39 Exactly how Nicon ended up is not completely clear but the documents readily available online point
|
||||||
|
Page generated in 0.0094 seconds, 29 queries |
|||||||